中國儲(chǔ)能網(wǎng)訊:近日,由亞洲開發(fā)銀行捐贈(zèng)、中興能源承建的巴基斯坦亞行風(fēng)光互補(bǔ)電源系統(tǒng)試點(diǎn)工程已經(jīng)完工,并順利完成一年運(yùn)維移交當(dāng)?shù)卣?。該?xiàng)目作為亞行示范項(xiàng)目,為巴基斯坦無電山區(qū)的村民解決用電難題提供了很好的示范作用。
Recently, ADB wind-solar hybrid power system pilot poject in Khushab, Punjab, Pakistan which is donated by Asia Development Bank (hereinafter referred to as “ADB”) has completed and hand over to local government after 1 year operation. As a pilot project, it provides a good example to solve power problems for residents of no-electricity mountain villages.
項(xiàng)目順利通過旁遮普省能源局和亞行代表團(tuán)驗(yàn)收
ADB Project is accepted by Punjab Energy Department and ADB Team
本項(xiàng)目位于巴基斯坦旁遮普省胡沙布地區(qū)的無電山區(qū)(Wadgal和Pheera兩個(gè)山村)。在夜晚,當(dāng)?shù)卮迕裰荒苁褂孟灎T和煤油燈進(jìn)行照明;在夏季,氣溫高達(dá)四五十度,當(dāng)?shù)卮迕駞s無法使用電風(fēng)扇降溫。無電給當(dāng)?shù)卮迕竦娜粘I顜砹藰O大的不便。
This small power plant is located in Wadgal and Pheera villages, the mountain villages of no electricity area in Khushab district, Punjab province, Pakistan. Villagers only use candles and oil light to provide light in the evening. In summer, the highest temperature is almost 50 degree Celsius, but villagers can’t use fans to cool down.
當(dāng)?shù)鼐用裥『⑼砩显诿河蜔粝聦W(xué)習(xí)
Resident child is studying with the oil light in the evening
為了改善當(dāng)?shù)鼐用竦纳瞽h(huán)境,基于WAPDA的電網(wǎng)規(guī)劃和當(dāng)?shù)氐娘L(fēng)力、太陽能資源,亞行決定在這里捐贈(zèng)一座風(fēng)光互補(bǔ)電源系統(tǒng)。中興能源憑借多年國內(nèi)外光伏項(xiàng)目實(shí)施經(jīng)驗(yàn),迅速脫穎而出成為本項(xiàng)目的EPC總承包方,負(fù)責(zé)該項(xiàng)目的實(shí)施。
To improve the living environment of local residents, ADB decide to donate a wind-solar hybrid power system here according WAPDA grid planning and local wind resource and solar resource. And Zonergy is in charge of the execution of this project as an ECP contactor, depend on abundant PV solar project experience all over the world.
盡管現(xiàn)場施工條件非常艱苦,地處無電山區(qū)深處,但中興能源的施工人員還是克服了種種困難,順利的完成了項(xiàng)目的實(shí)施。
Although the project site is located in very far no electricity and no water mountain area, and have a very hard environment, but Zonergy team overcome all the difficulties, and completed this project rapidly. Then let us to see the execution of this project as following:
本項(xiàng)目裝機(jī)容量共計(jì)55KW,包含2臺(tái)10KW風(fēng)機(jī)機(jī)組和1個(gè)35KV的光伏電站,年發(fā)電量為7萬多度,能滿足當(dāng)?shù)?0戶村民約560人、1所學(xué)校、1個(gè)清真寺的日常用電以及電站運(yùn)維自用電需求,很大程度地改善了當(dāng)?shù)卮迕竦纳钯|(zhì)量。
The capacity of this project is 55KW, include 2 sets of 10KW wind turbine generators and 1 set of 35KV PV solar power system. It will produce more than 70,000KWh power every year, to provide energy for 80 household 560 persons, and 1 school and 1 mosque, and will greatly improve life quality of local residents. Zonergy is in charge of designing, construction and 1 year O&M works as an EPC contactor.
項(xiàng)目建成后,亞行總部領(lǐng)導(dǎo)、旁省能源局領(lǐng)導(dǎo)等頻頻訪問參觀電站。該項(xiàng)目給當(dāng)?shù)責(zé)o電地區(qū)離網(wǎng)光伏項(xiàng)目提供了很好的示范作用。
After completion of the project, ADB head office and Punjab energy department visit power plant frequently. And it is a good example for local no electrical area in off grid PV solar project.
下面就讓我們來了解一下項(xiàng)目的情況
中興能源項(xiàng)目組與旁遮普省能源局領(lǐng)導(dǎo)、亞行項(xiàng)目組合影
Zonergy Team with Punjab Energy Department Leaders and ADB Team together
亞行總部領(lǐng)導(dǎo)參觀電站
ADB Head Office Visiting Power Plant
旁省能源局局長參觀電站
Punjab Energy Department Secretary Visiting Power Plant